In our country, construction has been and continues to be one of the pillars of the economy and a source of work. In this post we are going to study the retention of work as a way of guaranteeing the possible defects of any construction.
Scope of application and object
The retention of work as a guarantee in construction is part of the legal text contained in Law 38/1999, of November 5, on Building Regulations . The first articles of the aforementioned law define its scope, which is "the building process, understood as the action and result of constructing a permanent building, public or private…".
Similarly, in accordance with the provisions of Article 1, first paragraph, the aforementioned Law aims to " regulate the building process in its essential aspects, establishing the obligations and responsibilities of the agents involved in said process, as well as the necessary guarantees for its proper development , in order to ensure quality through compliance with the basic requirements of buildings and the adequate protection of the interests of users."
What is a retention of work?
A work retention consists of the reduction of a percentage (5%) within the total cost of a work, in favor of the contracting company, as an annual guarantee, to cover possible construction defects and other contingencies included in article 17.1 of the LOE.
Within the Statement of Reasons of the LOE , in point six we can find the following reference:
With regard to guarantees, the Law establishes, for residential buildings, the mandatory subscription by the builder, for a period of one year, of a material damage or surety insurance, or the retention by the developer of 5 percent of the cost of the work to deal with material damages caused by a deficient execution.
Article 19.1, in this same sense, establishes that “The system of guarantees required for the building works included in article 2 of this Law will be made effective in accordance with the obligation established in application of the second additional provision, taking as a reference the following guarantees:
a) Property damage insurance or surety insurance, to guarantee, for one year, compensation for material damages due to defects or flaws in execution that affect elements of completion or finishing of the works, which may be replaced by the retention by the promoter of 5 percent of the amount of the material execution of the work.”
As we can see in the explanatory memorandum, the law allows us to subscribe to damage or surety insurance or to make a retention, by the promoter, of 5% of the cost of the work.
In construction and service provision contracts extended to long periods, the usual practice is to make various payments distributed throughout the contract, instead of making a single payment.
Therefore, if you choose to use the retention of work, instead of insurance for damages or surety, we must retain the percentage indicated by law in each of the invoices that the developer is issuing.
Once the work is completed and delivered, if there are hidden defects or defects in the construction, the developer may use the amounts withheld to cover repair costs.
If there are no defects, the developer must return all the amounts discounted from the invoices for retention of work, within a maximum period of one year from the delivery of the work.
When does the year count start to return the amounts withheld?
As we have said, in the event that the work has been carried out as contractually foreseen, delivered on time and without any hidden defects, after one year, the developer must return the amounts withheld.
The possible problem arises when starting the year count. Well, in those cases where the receipt of the work has been signed, this will be the date that we must use.
If this acceptance document does not exist, we must comply with the provisions of article 6.4 of the Building Regulations Law :
"Unless expressly agreed otherwise, the reception of the work will take place within thirty days from the date of its completion, accredited in the final certificate of the work, a period that will run from the written notification to the developer. The reception will be understood as tacitly produced if thirty days after the date indicated the promoter had not revealed reservations or a reasoned rejection in writing. ”
However, the Jurisprudence has admitted the tactical acceptance within those thirty days, when there are unequivocal acts on the part of the payer, such as the reception of the work without reservations or the use of the construction.
Refusing, without just cause, to return the amounts withheld as a guarantee, contravenes article 1.256 of the Civil Code , which establishes that the validity and fulfillment of contracts cannot be left to the discretion of one of the contracting parties.
Conclusion
The retention of work is, as we have seen, a way of guaranteeing possible vices or defects arising in construction during the year following its making available. When we face situations like this, it is advisable to carefully study the correct way to proceed, as well as make the invoices with the retention in a clear and understandable way, to avoid further problems.
Álvarez Ramos Lawyers
Comments
-
Good morning.
My problem is that I initially did not include in the contract for the execution of the works with the Construction Company (I am the owner/developer of a single-family home), the retention of 5% of the final amount and now the Construction Company tells me that since I did not include it in the contract, I cannot retain that 5% (after how the work has gone, it is more than likely that defects will arise as I live in the home and observe them), that the Building Regulations Law only provides for it in Public Works if it has not been previously included in the contract.
I understand that even if it was not initially included in the contract, if it is provided for by law, it was not necessary to include it since they are required by law (if that were true).
I would ask you to clarify this last point for me.Thank you very much.
-
Good afternoon Miguel Ángel.
Unfortunately, we must agree with the construction company. The 5% withholding is another option (and not mandatory) to guarantee the execution of a contract, so if it's not agreed upon by the parties, it cannot be enforced. This doesn't mean, obviously, that the construction company is any less responsible for any defects that may occur. I'm afraid that the only solution to your case (barring an agreement with the construction company) is to wait until the work is completed and, if there is damage, file a claim under the corresponding LOE (Organic Law on the Construction of Property).
A greeting.
-
-
Good afternoon,
The 5% guarantee withholding must be applied to the masonry construction items, but if after the contract for the work or finishing work, they request industrialists, eg. carpentry, should the 5% withholding also be made?-
Good afternoon.
According to the law, it is stated that the retention of work will be applicable to the elements of completion or finishing of the works, so in principle in that case the retention would also have to be included.
A greeting.
-
-
Good afternoon, I need guidance on the return of 5%. I provided services to a company that builds houses in the Bio Bio region. They withheld 5% every month for 7 months. We finished our work in September. It's been 3 months and they still haven't refunded the withholding money. Now they tell me that at the end of January since the mimvu has not yet received the work. Is it fair or is it normal that they take so long to make the return, or is there an estimated term for said effect?
-
Good afternoon.
The maximum term to deliver the amounts is one year from the reception of the work, so that in principle they could take all that time. As for whether it is normal for them to take so long in this return, we must say that unfortunately it is. In the construction sector, payments take longer than usual, and when it comes to retention of work, the terms are usually close to a year.
A greeting.
-
-
Can the 5% withholding be made when you have done hourly work or work without a contract?
-
Good afternoon Enrique.
The 5% withholding is a guarantee that has nothing to do with the typical tax withholdings of the Treasury, so the answer in principle is yes. A separate contract should be made in which the existence of this retention and the obligation to return the amount once the work is completed is expressed.
A greeting.
-
-
The builders do not return on time and retain 10%, this is to favor the builder against the small contractors forced to receive the profit a year later and if it is a consortium the government asked for the money, all in favor of the octopuses
-
"The contracting of insurance by the builder or the retention of 5% by the developer in the event of defects in the finish of the building, is not legally required, without having been agreed in the contract"
AP Madrid, Sec. 21.ª, 8-11-2016 (SP / SENT / 886459) -
Dear Sirs,
I have read your article with interest as well as other published information, and doubts have arisen about the mandatory nature of insurance and / or retention and its entry into force as such. Since the Second Additional Provision of the LOE made explicit that it should be through Royal Decree that this obligation was regulated.
Along these lines, I have found a couple of publications, one of which is an excerpt below, taken from the Private Law Seminar at the University of Malaga.
I think it would be interesting to clarify and / or make references to the Royal Decrees that may have been approved in that regard. In a multitude of sources, especially the publications of the insurance companies, reference is made exclusively to article 19, 1a, 1b and 1c but it goes too far or does not mention / clarify what is reflected in the Second Additional, I understand that it is an opportunity to go further in the writing of your article.
Sincerely,
https://www.uma.es/seminario-derecho-privado/info/33002/mingorance-seguro/?set_language=en
«II. Mandatory insurance
A very notable novelty of the LOE is the consecration of the obligation to establish property damage or surety insurance, which is regulated in art. 19 of the LOE in relation to Additional Provision 2:
. one, by the builder, to guarantee, for one year, compensation for material damages for flaws or defects in execution that affect elements of completion or finishing of the works. Point out the art. 19.1.a) that this insurance may be replaced by the withholding by the promoter of 5% of the amount of the material execution of the work.
. another, by the developer, to guarantee, for three years, compensation for damages due to flaws or defects in construction elements or facilities that cause non-compliance with habitability requirements;
. and a third insurance, which must also be signed by the developer, to guarantee, for ten years, the material damages that originate in the structural elements of the building and that directly compromise its mechanical resistance and stability [1].
In any case, the obligation to subscribe to said precepts was conditioned to the provisions of the second additional provision. The initial drafting of Disp. Second additional only contemplated the mandatory nature of underwriting the insurance referred to in art. 19.1.c of the LOE [2] in the case of buildings whose main destination is housing, providing for the possibility that the government, by means of RD, would extend the obligation of other insurances to buildings whose main destination is housing. Likewise, a Royal Decree could establish the obligation to subscribe any of the guarantees provided for in article 19, for buildings intended for any use other than housing.
Law 53/2002, of December 30, on Fiscal, Administrative and Social Order Measures [3], modified the additional provision 2 of the LOE, in the sense that although as a general rule the mandatory nature of the subscription of the aforementioned insurance, an exception is established in the case of individual self-promotions of a single single-family home and it is clarified that such obligation is not applicable in the cases of rehabilitation of buildings intended mainly for housing whose projects were requested before the LOE [4 ].
Ultimately, the only one of the three insurances provided for in art. 19.1 currently mandatory according to the Law is the last of those mentioned, and only in relation to buildings whose destination is housing, the first two being discretionary establishment by the Government. "